2980 JOHNSTONVILLE

IN REVIEW
ADDITION & ALTERATION

Status mismatch

This permit has 12 inspection(s) on record but its status is IN REVIEW — not ISSUED. Inspections should only be performed on issued permits. Update the status if this permit has been issued.

Permit Timeline

⬤ In Review 9/28/2026
Issued
FOOTING 05/15/2026 PASS
UNDERSLAB PLUMBING 05/28/2026 PASS
SLAB 06/15/2026 PASS
SHEATHING 07/06/2026 PASS
FRAMING ROUGH 07/17/2026 PASS
ROUGH BUILDING 07/17/2026 C&R
ROUGH BUILDING 07/23/2026 PASS
INSULATION 07/23/2026 PASS
+4 More
Permit Finaled
Certificate Issued

Project Information

Edmunds #

—

MC #

MC2026-524

Issued Date

—

Finaled Date

—

Owner

GUY MERRITT HARRIS

Owner Address

2980 JOHNSTONVILLE RD, FORSYTH, GA

Contractor

GUY MERRITT HARRIS

Project Type

ADDITION & ALTERATION

Description

SUBWAY RENOVATION - INTERIOR RENOVATION INCLUDING ADDITION OF NEW STEEL STUD FRAMING WITH INSULATION AND GYPSUM BOARD, BEER CAVE, HUMIDOR, GAME ROOM, WINE DISPLAY, BEVERAGE COOLER, ICE CREAM/SOFT SERVE AREA, COFFEE BAR, ROLLER GRILL, DRINK STATION, RESTROOMS, OFFICE, DRY STORAGE, ELECTRICAL/MECHANICAL ROOM, CASH WRAP, PREP AREA, AND SEATING; PHASE 1 AND PHASE 2 WORK INCLUDING CMU EXTERIOR SEALING AND PAINTING AND STOREFRONT DOOR REFRAMING

Technical Details

Construction Type

V-B

Occupancy Group

M

Occupant Load

—

Square Footage

5901

Zoning

—

Sprinklers

NO

APN

—

Limitations

NONE

Inspection History

Date Type Inspector Result Notes
09/08/2026 CEILING COVER Tyler Adams PASS —
08/25/2026 TEMP TO PERM Tyler Adams PASS —
08/06/2026 CEILING COVERUP Tyler Adams PASS —
08/04/2026 CEILING COVERUP Tyler Adams CORRECT AND RECALL - LINESETS HAVE NOT BEEN BRAZED TOGETHER - DUCT WORK SEEMS TO BE INCOMPLETE - WATERLINES NOT INSULATED - ELECTRICAL NOT TERMINATED OVERHEAD
07/23/2026 ROUGH BUILDING Tyler Adams PASS —
07/23/2026 INSULATION Tyler Adams PASS —
07/17/2026 FRAMING ROUGH Tyler Adams PASS —
07/17/2026 ROUGH BUILDING Tyler Adams CORRECT AND RECALL PLUMBING ROUGH INCOMPLETE
07/06/2026 SHEATHING Tyler Adams PASS —
06/15/2026 SLAB Tyler Adams PASS —
05/28/2026 UNDERSLAB PLUMBING Tyler Adams PASS —
05/15/2026 FOOTING Tyler Adams PASS —

Schedule Inspection

This permit is IN REVIEW, not ISSUED. You can still schedule, but verify the permit status is correct first.