Permit Timeline
In Review
8/21/2026
Issued
8/25/2026
UNDERSLAB PLUMB
06/26/2026
PASS
FOUNDATION
07/10/2026
PASS
WALL SHEATHING
08/19/2026
C&R
PLUMBING-POOL
09/03/2026
PASS
POOL BASKET
09/03/2026
PASS
WALL SHEATHING
09/04/2026
PASS
INSULATION
10/08/2026
CANCE
COMBINATION ROUGH
10/08/2026
C&P
+4 More
Permit Finaled
Certificate Issued
Project Information
Edmunds #
—
MC #
MC2026-462
Issued Date
8/25/2026
Finaled Date
—
Owner
CHARLIE CANNON
Owner Address
600 KING ROAD, FORSYTH, GA 31029
Contractor
IVEY LEAGUE POOLS
Project Type
SWIMMING POOL
Description
INSTALL 18'X36' GUNITE POOL WITH CONCRETE DECKING
Technical Details
Construction Type
II-B
Occupancy Group
U
Occupant Load
N/A
Square Footage
1200
Zoning
—
Sprinklers
NO
APN
081 042
Limitations
NONE
Inspection History
| Date | Type | Inspector | Result | Notes |
|---|---|---|---|---|
| 10/16/2026 | INSULATION | Tyler Adams | PASS | — |
| 10/16/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 10/16/2026 | COMBINATION ROUGH | Andy Brumbalow | PASS | — |
| 10/09/2026 | COMBO ROUGH | Tyler Adams | CANCEL | — |
| 10/08/2026 | INSULATION | Tyler Adams | CANCEL | — |
| 10/08/2026 | COMBINATION ROUGH | Tyler Adams | CORRECT AND PROCEED | - insulate all waterlines in exterior walls - insulate all 3/4 hot waterlines - secure waterline to framing members in wall - replace flex duct out of dryer exhaust |
| 09/04/2026 | WALL SHEATHING | Tyler Adams | PASS | — |
| 09/03/2026 | PLUMBING-POOL | Tyler Adams | PASS | — |
| 09/03/2026 | POOL BASKET | Tyler Adams | PASS | — |
| 08/19/2026 | WALL SHEATHING | Kyle Golberg | CORRECT AND RECALL | SHEATHING unfinished |
| 07/10/2026 | FOUNDATION | Tyler Adams | PASS | — |
| 06/26/2026 | UNDERSLAB PLUMB | Tyler Adams | PASS | — |