Permit Timeline
In Review
5/20/2026
Issued
UNDERSLAB PLUMBING
06/09/2026
PASS
FOUNDATION
06/16/2026
PASS
ROUGH BUILDING
09/11/2026
C&R
SHEATHING
09/11/2026
C&R
MOISTURE BARRIER
09/11/2026
C&R
SHEATHING
09/14/2026
PASS
MOISTURE BARRIER
09/14/2026
PASS
ROUGH BUILDING
09/22/2026
C&P
+2 More
Permit Finaled
Certificate Issued
Project Information
Edmunds #
P-100626
MC #
MC2026-355
Issued Date
—
Finaled Date
—
Owner
MEREDITH HOMES INC
Owner Address
76 VAUGHN SCHOOL RD, GRIFFIN, GA 30223
Contractor
MEREDITH HOMES INC
Project Type
NEW SINGLE FAMILY RESIDENTIAL
Description
NEW CONSTRUCTION
Technical Details
Construction Type
V-B
Occupancy Group
R-3
Occupant Load
N/A
Square Footage
2,752
Zoning
A-R
Sprinklers
NO
APN
052 019A
Limitations
NONE
Inspection History
| Date | Type | Inspector | Result | Notes |
|---|---|---|---|---|
| 09/29/2026 | INSULATION | Tyler Adams | PASS | — |
| 09/29/2026 | ROUGH BUILDING | Tyler Adams | PASS | — |
| 09/22/2026 | ROUGH BUILDING | Tyler Adams | CORRECT AND PROCEED | - NO WATER ON TUB AND DRAINS TO SECOND FLOOR - DRAFT BLOCK MECHANICAL CHASE IN LEFT SECOND FLOOR BEDROOM AT TOP OF STAIRS, THE DIAGONAL PORTION |
| 09/14/2026 | SHEATHING | Tyler Adams | PASS | — |
| 09/14/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 09/11/2026 | ROUGH BUILDING | Tyler Adams | CORRECT AND RECALL | - has not passed sheathing or moisture barrier, 90% of siding is installed - draft blocking over panel - no pressure test on waterlines - stud shoes are missing nails - missing nail guards over cables through framing members through out - line sets and condensate are out of wall - back porch ceiling covered prior to rough - frame mechanical chases, and draft block said chases - bath fan in master water closet does not have a grommet on cable entrance - secure and protect cables and wires in attic space a space over garage needs an accessible entrance - space over master bedroom needs an accessible entrance - seal holes beneath tub on second floor - no water on drains and tubs - bath fan and second floor bathroom does not have grommet at cable entrance - double stud shoe need over left drain arm in second floor bathroom - bath fan and master bathroom does not have grommet at cable entrance |
| 09/11/2026 | SHEATHING | Tyler Adams | CORRECT AND RECALL | - MOISTURE BARRIER AND SIDING INSTALLED PRIOR TO PASSING SHEATHING |
| 09/11/2026 | MOISTURE BARRIER | Tyler Adams | CORRECT AND RECALL | SIDING INSTALLED PRIOR TO PASSING SHEATHING AND MOISTURE BARRIER |
| 06/16/2026 | FOUNDATION | Tyler Adams | PASS | — |
| 06/09/2026 | UNDERSLAB PLUMBING | Tyler Adams | PASS | — |