Permit Timeline
In Review
11/17/2025
Issued
8/20/2026
FOOTING
12/11/2025
PASS
UNDERSLAB PLUMBING
12/23/2025
PASS
SLAB GRADE
1/13/2026
PASS
T-POLE
3/3/2026
PASS
SHEATHING
06/02/2026
C&R
WALL SHEATHING
06/26/2026
PASS
MOISTURE BARRIER
07/23/2026
PASS
PLUMBING
07/23/2026
PASS
+19 More
Permit Finaled
Certificate Issued
Project Information
Edmunds #
P-431125
MC #
MC2026-228
Issued Date
8/20/2026
Finaled Date
—
Owner
JAGDISH FORSYTH LLC
Owner Address
P.O BOX 1059, SUWANEE, GA 30024
Contractor
IDENTITI
Project Type
SIGN
Description
NEW GROUND SIGN
Technical Details
Construction Type
II-B
Occupancy Group
U
Occupant Load
N/A
Square Footage
72
Zoning
C
Sprinklers
NO
APN
F14 036
Limitations
NONE
Inspection History
| Date | Type | Inspector | Result | Notes |
|---|---|---|---|---|
| 3/3/2026 | T-POLE | TYLER ADAMS | PASS | — |
| 12/23/2025 | UNDERSLAB PLUMBING | TYLER ADAMS | PASS | — |
| 12/11/2025 | FOOTING | TYLER ADAMS | PASS | — |
| 10/26/2026 | INSULATION | Tyler Adams | PASS | — |
| 10/20/2026 | CEILING COVER | Tyler Adams | PASS | — |
| 10/16/2026 | ROUGH BUILDING | Tyler Adams | CORRECT AND PROCEED | - MISSING DOUBLE HANGER IN SOUTH STAIRWELL - DRAFT BLOCK CONCEALED SPACE BETWEEN BATHROOMS IN ROOMS 102 AND 104 - DRAFT BLOCK CONCEALED SPACE BETWEEN BATHROOMS IN ROOMS 101 AND 103 - BOCA PLATE OVER DRAIN THROUGH SILL PLATE IN KITCHEN ROOM 101 - INSULATE ALL 3/4 INCH AND LARGER HOT WATERLINES OVERHEAD IN ROOMS - NAIL GUARDS NEEDED OVER 4 INCH THROUGH STUDS IN EMPLOYEE BREAK ROOM - BOCA PLATE OVER DRAIN THROUGH SILL PLATE LEFT SIDE WOMEN’S BATHROOM |
| 10/16/2026 | CEILING COVER | Tyler Adams | PASS | — |
| 1/13/2026 | SLAB GRADE | TYLER ADAMS | PASS | — |
| 09/22/2026 | CEILING COVERUP | Tyler Adams | PASS | — |
| 09/21/2026 | CEILING COVERUP | Tyler Adams | CORRECT AND RECALL | - MULTIPLE BREAKS ON EXHAUST PIPING IN BATHROOM CEILINGS OF THIRD AND FOURTH FLOOR - ELECTRICAL INCOMPLETE IN MOST OF THIRD AND FOURTH FLOOR BATHROOMS, LIGHTING OUTLET BOXES NOT SET - FRAMING FOR HARD CEILING INCOMPLETE IN MHALF THE BATHROOMS ON THIRD FLOOR |
| 09/14/2026 | INSULATION | Tyler Adams | PASS | — |
| 09/10/2026 | ROUGH BUILDING | Tyler Adams | PASS | — |
| 08/31/2026 | INSULATION | Tyler Adams | PASS | — |
| 08/25/2026 | CEILING COVERUP | Tyler Adams | PASS | — |
| 08/24/2026 | CEILING COVERUP | Tyler Adams | PASS | — |
| 08/24/2026 | ROUGH BUILDING | Tyler Adams | CORRECT AND PROCEED | - BOCA PLATES REQUIRED OVER PLUMBING PENETRATIONS TO TOP AND BOTTOM PLATE WHERE WITH IN 1.5” OF OUTSIDE EDGE OF FRAMING MEMBER. MISSING THROUGH OUT |
| 08/17/2026 | ROUGH BUILDING | Tyler Adams | CORRECT AND PROCEED | - FIRE SEAL ALL CHASES - REMOVE GREEN BOND SCREW FROM ALL SUB PANELS - INSULATE ALL 3/4 HOT WATERLINES - BOCA PLATES REQUIRED OVER ALL WATERLINE AND DWV THROUGH TOP AND BOTTOM PLATE WHERE PENETRATIONS ARE WITH IN 1.5 INCHES OF OUTSIDE EDGE OF FRAMING MEMBER - FIREBLOCK UNUSED OPENINGS IN TOP AND BOTTOM PLATES - MISSING DOUBLE HANGERS IN STAIR WELL |
| 07/27/2026 | FOOTING | Tyler Adams | PASS | — |
| 07/27/2026 | UNDERSLAB PLUMBING | Tyler Adams | PASS | — |
| 07/27/2026 | SLAB GRADE | Tyler Adams | PASS | — |
| 07/27/2026 | T-POLE | Tyler Adams | PASS | — |
| 07/27/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 07/27/2026 | PLUMBING | Tyler Adams | PASS | — |
| 07/23/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 07/23/2026 | PLUMBING | Tyler Adams | PASS | — |
| 06/26/2026 | WALL SHEATHING | Tyler Adams | PASS | — |
| 06/02/2026 | SHEATHING | Tyler Adams | CORRECT AND RECALL | - NAIL OFF EVERY 6 INCHES ALONG THE OUTSIDE OF EDGE OF EXTERIOR SHEATHING, INCLUDING HORIZONTAL JOINTS AT BLOCKING, SOME HAS BEEN DONE SOME HAS NOT. - HAVE FRAMERS CHECK FOR OVER PRESSURE ON PNEUMATIC FRAMING GUNS TO INSURE THAT NAILS ARE NOT OVER DRIVEN |