Permit Timeline
In Review
5/7/2026
Issued
05/07/2026
SLAB GRADE
05/15/2026
PASS
SHEATHING
05/28/2026
PASS
MOISTURE BARRIER
06/09/2026
PASS
COMBO ROUGH
06/12/2026
C&P
INSULATION
06/17/2026
CANCE
COMBINATION ROUGH
06/18/2026
PASS
INSULATION
06/18/2026
PASS
TEMP TO PERM
06/23/2026
PASS
+1 More
Permit Finaled
8/11/2026
Certificate Issued
10/26/2026
Project Information
Edmunds #
P-310526
MC #
MC2026-158
Issued Date
05/07/2026
Finaled Date
8/11/2026
Owner
J.E. ROUSH & COMPANY, LLC
Owner Address
58 LOGWALL CHURCH RD, FORSYTH, GA 31029
Contractor
J.E. ROUSH & COMPANY, LLC
Project Type
NEW SINGLE FAMILY RESIDENTIAL
Description
NEW SINGLE FAMILY DWELLING
Technical Details
Construction Type
V-B
Occupancy Group
R-3
Occupant Load
N/A
Square Footage
2880
Zoning
A-G
Sprinklers
NO
APN
027028F
Limitations
NONE
Inspection History
| Date | Type | Inspector | Result | Notes |
|---|---|---|---|---|
| 08/11/2026 | FINAL | Tyler Adams | PASS | — |
| 06/23/2026 | TEMP TO PERM | Tyler Adams | PASS | — |
| 06/18/2026 | COMBINATION ROUGH | Tyler Adams | PASS | — |
| 06/18/2026 | INSULATION | Tyler Adams | PASS | — |
| 06/17/2026 | INSULATION | Tyler Adams | CANCEL | — |
| 06/12/2026 | COMBO ROUGH | Tyler Adams | CORRECT AND PROCEED | - no pressure on waterlines - stud shoes need to be installed with 10d nails not Sheetrock screws - anchor needed with in 12 inches right side of back door - missing insulation and vapor barrier behind tub on exterior wall |
| 06/09/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 05/28/2026 | SHEATHING | Tyler Adams | PASS | — |
| 05/15/2026 | SLAB GRADE | Tyler Adams | PASS | — |