Permit Timeline
In Review
5/7/2026
Issued
UNDERSLAB PLUMBING
05/19/2026
PASS
SLAB GRADE
05/21/2026
PASS
WALL SHEATHING
06/24/2026
PASS
ROUGH BUILDING
07/31/2026
C&P
MOISTURE BARRIER
07/31/2026
PASS
INSULATION
08/05/2026
PASS
ROUGH BUILDING
08/05/2026
PASS
PERMANENT SERVI
10/06/2026
PASS
Permit Finaled
Certificate Issued
Project Information
Edmunds #
P-290526
MC #
MC2026-157
Issued Date
—
Finaled Date
—
Owner
4G LAND LLC
Owner Address
765 REHOBOTH CHURCH ROAD, GRIFFIN, GA 30223
Contractor
4G LAND LLC
Project Type
NEW SINGLE FAMILY RESIDENTIAL
Description
NEW SFR
Technical Details
Construction Type
—
Occupancy Group
—
Occupant Load
—
Square Footage
5728
Zoning
—
Sprinklers
—
APN
34050
Limitations
—
Inspection History
| Date | Type | Inspector | Result | Notes |
|---|---|---|---|---|
| 10/06/2026 | PERMANENT SERVI | Tyler Adams | PASS | — |
| 08/05/2026 | INSULATION | Tyler Adams | PASS | — |
| 08/05/2026 | ROUGH BUILDING | Tyler Adams | PASS | — |
| 07/31/2026 | ROUGH BUILDING | Tyler Adams | CORRECT AND PROCEED | - stud shoes over drain arm to vanity in powder room - no pressure on waterline - missing two stud shoes in master bathroom at left and right vanity - missing Boca plate through bottom plate over waterlines to shower in master closet |
| 07/31/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 06/24/2026 | WALL SHEATHING | Tyler Adams | PASS | — |
| 05/21/2026 | SLAB GRADE | Tyler Adams | PASS | — |
| 05/19/2026 | UNDERSLAB PLUMBING | Tyler Adams | PASS | — |