Permit Timeline
In Review
5/4/2026
Issued
05/04/2026
UNDERSLAB PLUMBING
05/15/2026
PASS
SLAB ON GRADE
05/19/2026
PASS
SHEATHING
06/01/2026
PASS
MOISTURE BARRIER
06/03/2026
PASS
COMBO ROUGH
06/09/2026
C&P
COMBO ROUGH
06/12/2026
PASS
INSULATION
06/17/2026
CANCE
INSULATION
06/18/2026
PASS
+2 More
Permit Finaled
9/16/2026
Certificate Issued
10/16/2026
Project Information
Edmunds #
P-250526
MC #
MC2026-151
Issued Date
05/04/2026
Finaled Date
9/16/2026
Owner
TRADEMARK QUAILTY HOMES
Owner Address
P.O 926, GREENVILLE, GA 30222
Contractor
TRADEMARK QUAILTY HOMES
Project Type
NEW SINGLE FAMILY RESIDENTIAL
Description
NEW SFR
Technical Details
Construction Type
V-B
Occupancy Group
R-3
Occupant Load
N/A
Square Footage
3872
Zoning
A-R
Sprinklers
NO
APN
031 022A
Limitations
NONE
Inspection History
| Date | Type | Inspector | Result | Notes |
|---|---|---|---|---|
| 09/16/2026 | FINAL | Tyler Adams | CORRECT AND RECALL | - EXTEND CONDENSATE DRAIN AWAY FROM FOUNDATION - DOOR TO MASTER BATHROOM OFF THE HINGES |
| 07/23/2026 | PERMANENT SERVICE | Tyler Adams | PASS | — |
| 06/18/2026 | INSULATION | Tyler Adams | PASS | — |
| 06/17/2026 | INSULATION | Tyler Adams | CANCEL | — |
| 06/12/2026 | COMBO ROUGH | Tyler Adams | PASS | — |
| 06/09/2026 | COMBO ROUGH | Tyler Adams | CORRECT AND PROCEED | - ufer ground needs to be accessible, no box or hand hole installed - fir out wall at low voltage box to maintain r value - missing moisture barrier and insulation behind tub inserts on exterior walls - possible leak beneath first floor tub, check before covering - |
| 06/03/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 06/01/2026 | SHEATHING | Tyler Adams | PASS | — |
| 05/19/2026 | SLAB ON GRADE | Tyler Adams | PASS | — |
| 05/15/2026 | UNDERSLAB PLUMBING | Tyler Adams | PASS | — |