Permit Timeline
In Review
3/31/2026
Issued
9/30/2026
SHEATHING
05/20/2026
PASS
MOISTURE BARRIER
06/04/2026
PASS
COMBO ROUGH
06/04/2026
C&P
INSULATION
06/09/2026
PASS
TEMP TO PERM
07/24/2026
C&P
FINAL
09/29/2026
PASS
Permit Finaled
9/29/2026
Certificate Issued
10/24/2026
Project Information
Edmunds #
P-230426
MC #
MC2026-132
Issued Date
9/30/2026
Finaled Date
9/29/2026
Owner
LOVETT SERVICES, INC
Owner Address
7450 MOSELEY DIXON RD, MACON, GA 31220
Contractor
LOVETT SERVICES, INC
Project Type
NEW SINGLE FAMILY RESIDENTIAL
Description
NEW SFR
Technical Details
Construction Type
V-B
Occupancy Group
R-3
Occupant Load
N/A
Square Footage
4842
Zoning
R-1
Sprinklers
NO
APN
084 001
Limitations
NONE
Inspection History
| Date | Type | Inspector | Result | Notes |
|---|---|---|---|---|
| 09/29/2026 | FINAL | Tyler Adams | PASS | — |
| 07/24/2026 | TEMP TO PERM | Tyler Adams | CORRECT AND PROCEED | - TIE LOOSE WIRES IN LEFT SERVICE DISCONNECT INTO A BREAKER OR SAFE OFF - MISSING MACHINE SCREW AT PANEL COVER - FILL IN MISSING BREAKER SPACE IN PANEL |
| 06/09/2026 | INSULATION | Tyler Adams | PASS | — |
| 06/04/2026 | MOISTURE BARRIER | Tyler Adams | PASS | — |
| 06/04/2026 | COMBO ROUGH | Tyler Adams | CORRECT AND PROCEED | 1. BOND TO UFER 2. BOND TO GAS LINe |
| 05/20/2026 | SHEATHING | Tyler Adams | PASS | — |