787 LASSITER RD

FINALED
NEW SINGLE FAMILY RESIDENTIAL

Permit Timeline

In Review 3/27/2026
Issued 3/25/2026
SHEATHING 05/18/2026 PASS
COMBINATION ROUGH 05/18/2026 C&R
MOISTURE BARRIER 05/26/2026 PASS
COMBINATION ROUGH 05/26/2026 PASS
INSULATION 06/05/2026 PASS
PERMANENT SERVICE 07/30/2026 PASS
FINAL 08/18/2026 NOT R
FINAL 10/06/2026 C&R
+1 More
Permit Finaled 10/23/2026
Certificate Issued 10/26/2026

Project Information

Edmunds #

P-170426

MC #

MC2026-130

Issued Date

3/25/2026

Finaled Date

10/23/2026

Owner

WILLIAM & HEATHER HONEA

Owner Address

787 LASSITER RD, FORSYTH, GA 31029

Contractor

WILLIAM & HEATHER HONEA

Project Type

NEW SINGLE FAMILY RESIDENTIAL

Description

NEW SFR

Technical Details

Construction Type

V-B

Occupancy Group

R-3

Occupant Load

N/A

Square Footage

4747

Zoning

A-R

Sprinklers

NO

APN

061 015J

Limitations

NONE

Inspection History

Date Type Inspector Result Notes
10/23/2026 FINAL Tyler Adams PASS —
10/06/2026 FINAL Tyler Adams CORRECT AND RECALL - BROKEN HARDI TRIM RIGHT OF GARAGE DOOR - LABEL AC CONDENSERS IN RELATION TO THEIR BREAKER - PIPE CONDENSATE DRAINS AWAY FROM FOUNDATION - PAINT EXTERIOR BLACK IRON GAS LINE AND FITTINGS
08/18/2026 FINAL Kyle Golberg NOT READY —
07/30/2026 PERMANENT SERVICE Tyler Adams PASS —
06/05/2026 INSULATION Tyler Adams PASS —
05/26/2026 MOISTURE BARRIER Tyler Adams PASS —
05/26/2026 COMBINATION ROUGH Tyler Adams PASS —
05/18/2026 SHEATHING Tyler Adams PASS —
05/18/2026 COMBINATION ROUGH Tyler Adams CORRECT AND RECALL 1. MOISTURE BARRIER AND WINDOWS NOT INSTALLED 2. SILL PLATE ANCHORS REQUIRED WITH-IN 12” OF ALL BREAKS AND JOINTS IN EXTERIOR SILL PLATE 3. NO TEST ON WATERLINES AND TUBS 4. NO EHAUST FAN INSTALLED IN WATER CLOSET OF MASTER BATHROOM 5. SMOKE DETECTOR IN LIVING ROOM CEILING NEEDS TO BE WITH-IN 12” OF HIGH POINT OF CEILING

Schedule Inspection

Quick Reference

Edmunds #

P-170426

MC #

MC2026-130

Quick Add Inspection